Unconventional applications
with single frequency DGPS
RAJNEESH GUPTA, VIVEK BANSAL, BRIG M C DHAMIJA (RETD) |
Even though apparently it falls short of
double tertiary class II standard, the fact
remains that the average correction per
linear km is less than 5 mm and per leg of
average distance 8 km (i.e. 107÷13) the
error is with in 6 cms for each leg of 8 km,
which after adjustment where accurate BM
heights are known is acceptable for most
surveys relating to highways and pipeline & other infrastructure surveys as well
as are adequate for topo surveys. Where
VI for contouring is 1 meter or more. |
| DEM/DTM |
Under normal conditions, Single
Frequency DGPS stipulates that 15
epoch acquisition of data is adequate
to achieve the specified accuracy in X,
Y & Z. For any DEM / DTM all threevalues of X, Y & Z are necessary. In
our trials, an area of about 20 Acres
was taken up for preparation of DEM
/ DTM. Single frequency DGPS was
used in Stop & Go mode for acquisition
of xyz for points spaced approx every
5 meters. The Base was established in
centre of area and Rovers were initialized
using initializing bar. The recording
interval was kept at one second so that
time for data acquisition at each point
is not more than 20 seconds. Besides
one Base station, 3 Rovers were utilized
for data acquisition in grid pattern. In
this configuration, the XYZ for approx
3000 points acquired in one day, which
was considered to be very economical
out turn as compared with other
conventional instruments. Alongwith
the grid pattern data acquisition, the
surveyors picked up positions of breakpoints as well as features of interest.
Repeat observation was taken on well
spread 50 points for comparison. The
average ellipsoidal height discrepancy
on the repeat points was with in 1cm
and the maximum discrepancy in repeat
point at extreme ends was with in 2
cms. Standard software with 8 degree
polynomial was used for drawing DEM.
A check line at random was carried
out which showed that all elevations
were in agreement with in 1.5 cm.
L Section & Cross Section
In the third trial one L section of
500 meters with cross section at
every 50 meters was observed by
single frequency DGPS in stop & go
Kinematic mode and post processed
part of this was checked using the
auto level. The discrepancy in relative
ellipsoidal heights for this small area
was maximum of 3mm at the extremity.
As Built Survey
The fourth project involving survey of ‘As Built’ of oil pipeline was carried out
by surveyors M/s Punj Lloyd for their
project Dahej-Uran gas Pipeline (DUPL)
for GAIL. The pipeline had been laid over
a distance of 132 km with turns, curves,
and river crossings. The work involved
in co-ordinating turns as well as level
grading that the as built pipelines adhered
to. This was successfully carried out
using single frequency DGPS in leap-frog
mode by surveyors of M/s Punj Lloyd
with our active involvement and under the
continued monitoring by their consultant
and resulted in considerable time saving,
as compared to the conventional systems.
|
| Discussion |
In the absence of MSL bench marks,
all elevations over longer distance were
converted to orthometric heights using
EGM-96. However where ever SOI
leveling bench marks are made available
a suitable Geoid model with interpolation
based on suitable polynomial curve
fitting should meet the specifications
of project indenters. Presently hardlyany contactor has access to SOI bench
marks and they usually commence their
work from an arbitrarily established
point. However by & large accuracy of
single tertiary class II suffices for their
projects. Accordingly they are able to meet
their client’s requirements with relative
difference of ellipsoidal heights with
EGM96 orthometric heights datumed to
mean value of elevation of beginning point
which is derived from SOI TOPO maps,
so that the elevation data is not too much
in variation with absolute M.S.L. elevation
in the project area. Hopefully, this
situation would improve with technology
awareness and opening up measures that
SOI has initiated for data availability as
well as availability of INDGEOID on
which G&RB, Survey of India is currently
working. We hope this Geoid model will
be available to private surveyors as well.
The 118 km road line was completed in
3 working days. The DEM observations
and processing was completed in 2
days and the L section X section was
completed in one working day. The asbuilt
pipe line of 130 km (approx) was
completed in about 25 days under constant
scrutiny of the consultant’s engineers. |
| Concluding remarks |
We may also add a word of caution that
as far as possible in road/canal/pipeline
projects in generally fl at areas the GPS
derived heights should as a rule be done
section by section of limited lengths.
In extremely fl at areas where the slope
measurement is very critical to the project
a few small sections of spirit leveling as
checkup may be done. One must make
appreciation of the tolerance threshold
and if this threshold is single tertiary
class II, the relative height information
can be confidently derived by single
frequency DGPS, in leap frog procedure.
Single Frequency DGPS are very
versatile, handy and give precise results.
The cost of ownership is much lower
than those of Dual Frequency as such
ROI is realizable in just one or two
survey projects. Dual frequency DGPS
of course have their own applications. |
| Acknowledgements |
The initial inspiration & guidance for
undertaking this study was provided by
Brig (Dr.) B. Nagarajan, Director, Geodetic & Research Branch, Survey of India.
The second impetus has been various
articles & regular column in various
issues of Co-ordinates by Dr. Muneendra
Kumar, Chief Geodesist (Retd.) USNGIA.
Dr. Kumar has been a strong proponent
of utilizing ellipsoidal heights for
engineering and Topo survey projects.
The acknowledgement can not be complete
without mentioning Prof. P. Misra whose
pearls of wisdom exhorts that merely
having high level of knowledge of
technology is of no help to any body. The
challenge before professionals is to be
aware of the problem solving abilities of
technology and then utilize it for the same.
|
| References |
1 ) Redefinition of Indian Geodetic datums
Horizontal and Vertical, Brig (Dr.)
B. Nagarajan, R.K. Sawhney, Coordinates
Vol. III issue 4 April 2007
2 ) Determining of Local gravimetric
Geoid, S.K. Singh, Brig (Dr) B.
Nagarajan, P.K. Garg, Co-ordinates
Vol. III issue 2, Feb 2007.
3 ) Geoid Vol. III issue, Jan-March 2007.
4 ) GPS Based control points for
mapping, Jayanta Kumar Ghosh,
Ojaswa Sarmg, Amit Goyal,l
5 ) Co-ordinates Vol. II issue 10 Oct
2006.A Cost Effective GPS leveling
method versus conventional method
for typical surveying application. Mr.
Metin Soycan, GIS Development Asia
Pacific, Vol 10 issue 8 Aug 2006
6 ) Ellipsoidal heights and engineering
applications, Muneendra Kumar Ph.D,
Co-ordinates Vol. III issue 1, Jan 2006.
7 )Global usage of Ellipsoidal Heights
Dr. Muneendra Kumar, Coordinates
Vol. issue II July 2005
8 ) Orthometric Heights From
GPS-Leveling Observations,
Brig. (Dr.) B. Nagarajan, S.K.
Singh, GIS Development Vol.
9 issue 4 April 2005. |
| |
 |
|
 |
Vivek Bansal
Sr. Asst. Manager,
Pan India Consultants,
Gurgaon, India
paie@bol.net.in
|
 |
|
|
| |
| << Previous Page |
| September 2007 |
|
|
|